FNDC Contract 7/23/107 - EW PH3 - West Coast Road, Pangaru

This tender is using the new split file responses feature on GETS. The agency has indicated that they would like to receive responses separated by price and non price components. Please keep this in mind when preparing your response for submission via GETS.

Details

Tender Closed
RFx ID : 29582622
Tender Name : FNDC Contract 7/23/107 - EW PH3 - West Coast Road, Pangaru
Reference # : 7/23/107
Open Date : Wednesday, 12 June 2024 3:00 PM (Pacific/Auckland UTC+12:00)
Close Date  : Thursday, 11 July 2024 5:00 PM (Pacific/Auckland UTC+12:00)
Tender Type : Request for Tenders (RFT)
Tender Coverage : Sole Agency  [?]
Categories :
  • 72140000 - Heavy construction services
  • 72150000 - Specialized trade construction and maintenance services
  • 95000000 - Land and Buildings and Structures and Thoroughfares
Regions:
  • Northland
Exemption Reason : None
Required Pre-qualifications : None
Contact : Nicki Warner
094015186
Alternate Physical Delivery Address  :
Alternate Physical Fax Number  :
Overview

This Contract is for the construction of an embankment with 3 rows of H5 treated timber piles 300mm diameter and 8m deep with column centers of 1.5m, installation of a new 600mm diameter
flexible plastic drain pipe and reinstatement of the existing road.

The scope of the physical works comprises of:
• Traffic Management, with special emphasis that the Contractor shall ensure that access is to be maintained at all times along the West Coast Road while works are underway.
• Vegetation clearing. I am in the process of working with an Ecologist who will advise whether we need a consent and what the Contractor has to comply with apart from the E&S Control Plan
• Installation of 3 rows of 300mm Ø driven timber piles at 8.0m deep @ 1.5m c/c with MSE embankment above comprising of 3 layers of 6.0m long TENSAR RE520 geogrid..
• Pavement reinstatement (with stabilised basecourse)

Far North District Council (The Principal) is seeking contractors who will:
• Complete the works on or before the Due Date for Completion
• Assist in providing a safe and more efficient network, minimising costs and increasing user satisfaction with the network;
• Implement and maintain high standards of health & safety and environmental practices and procedures;
• Undertake all practical measures to mitigate the social and environmental impacts of their activities;
• Provide value for money and increased price certainty in the procurement and construction of the Contract Works;
• Implement proactive strategies to enable the timely completion of the Contract Works;
• Develop and implement innovative work methods and/or Materials that result in enhanced performance and a cost-effective design;
• Commit to a co-operative approach to the Contract through a partnering process.