You are not logged in.

No.4 Road Bridge Replacement Physical Works

This tender is using the new split file responses feature on GETS. The agency has indicated that they would like to receive responses separated by price and non price components. Please keep this in mind when preparing your response for submission via GETS.

Details

RFx ID : 30005961
Tender Name : No.4 Road Bridge Replacement Physical Works
Reference # : 24-1075
Open Date : Tuesday, 20 August 2024 8:00 AM (Pacific/Auckland UTC+12:00)
Close Date  : Tuesday, 24 September 2024 5:00 PM (Pacific/Auckland UTC+12:00)
Tender Type : Request for Tenders (RFT)
Tender Coverage : Sole Agency  [?]
Categories :
  • 72141100 - Infrastructure building and surfacing and paving services
Regions:
  • Bay of Plenty
Exemption Reason : None
Required Pre-qualifications : None
Contact : Laraine Jackett
Procurement@westernbay.govt.nz
Alternate Physical Delivery Address  :
Alternate Physical Fax Number  :
Overview

Western Bay of Plenty District Council (Western Bay) wishes to procure construction of a new bridge on No. 4 Road in Te Puke, Bay of Plenty. This is a significant project both for Council and the local community. The bridge is to be completed in early March 2025 to support the local economy and the timely transport of the kiwifruit harvest. The bridge will provide permanent, reliable and secure access for No 4 Road residents.

This will be a new single span bridge comprising of steel girders made composite with a reinforced concrete bridge deck. The superstructure will be supported by new cast in-situ abutments founded on new piles. New instream scour protection and works in the riverbed is also required as part of the construction.

The Principal is looking for a Contractor who can:
• Implement proactive strategies to enable the timely completion of the Contract Works, including maintaining traffic access of the bailey bridge throughout construction of the new bridge.
• Develop and implement innovative work methods and/or materials that result in enhanced performance and an overall cost saving.
• Comply with all conditions and requirements of the contract including quality assurance, and health and safety.
• Work collaboratively with the Principal and Designer to implement the works.
• Keep local residents, road users and Council fully up to date as work progresses particularly in regard to road closures and other traffic management measures that affect road access.
• Manage environmental and cultural effects of the construction works.

Supplier briefing (via MS Teams) 15:00 Monday 26 August 2024. PLEASE RSVP by 16:00 Friday 23 August 2024 to: Sam.Sherlaw@beca.com

Refer to Attachments for details about this RFT.