You are not logged in.

Main Contractor for SIP: D: Gymnasium Upgrade Including Toilets at Kings High School

Details

Tender Closed
RFx ID : 26162752
Tender Name : Main Contractor for SIP: D: Gymnasium Upgrade Including Toilets at Kings High School
Reference # : 213215
Open Date : Friday, 12 August 2022 3:00 PM (Pacific/Auckland UTC+12:00)
Close Date  : Tuesday, 13 September 2022 5:00 PM (Pacific/Auckland UTC+12:00)
Department/Business Unit : Board of Trustees - Approve by BoT - ie. School Principal
Tender Type : Request for Tenders (RFT)
Tender Coverage : Sole Agency  [?]
Categories :
  • 72000000 - Building and Facility Construction and Maintenance Services
Regions:
  • Otago
Exemption Reason : None
Required Pre-qualifications : None
Contact : All communications must take place through the GETS Question & Answer function.
Alternate Physical Delivery Address  : All submissions to be made through the GETS website.
Alternate Physical Fax Number  :
Overview

King's High School is a state single-sex boys' secondary school located in Bayview Road, South Dunedin.

• King’s High School is committed to Building Men for Life by encouraging and challenging students to strive for personal excellence in all their pursuits. High standards and expectations are reinforced through the traditional values that are modelled, taught and expected. This vision is realised through the pursuit and promotion of personal excellence. The school encourages, inspires and expects each boy to be the best that he can be, whether in the classroom, on the stage or in the sporting arena

• The school has a proud sporting culture and the Gymnasium is the heart and soul of the sporting environment. The existing Gymnasium was constructed in the 1970’s, with a major refurbishment in 2009. This internal upgrade is designed to bring the facilities up to the latest Ministry of Education standards to serve the school for the foreseeable future.

• Project consultants are:
Lloyd Napper Logic Group – Project Manager
Lead Designer – Mike Sowman, Mike Sowman Design
Fire Engineer – Nimish Deo, Fire Design Solutions
Structural Engineer – David Hand, Hanlon & Partners Ltd
Mechanical Engineer – Glenn Hill, Aircomm
Electrical Engineer – Tony Ross, Pedersen Read
Plumbing and Drainage)– Steve Diggle, Foley Plumbing

Required solution (method and approach).

The Contract Works required are (refer to attached drawings for full details):
- Convert existing Change Rooms 1 & 2 (East) to a new Recovery Room and refurbished Toilets with new ventilation, insulation and plumbing and drainage. The Recovery Room floor is to be strengthened, and the Toilet floor is to be reshaped with a new sluice drain. Infill existing external windows. Note: This section of work is to be priced separately. Dependent upon the tender price, it may need to be delayed as a second stage when further Ministry of Education funding is made available to the school (refer to ‘Schedule of Prices’ spreadsheet ‘Trade Summary Toilets’). This will be discussed with the successful contractor

- Convert the existing Squash Court into an Analysis Room with a new external opening complete with a ramp / stair entry and grid ceiling with mechanical ventilation and ceiling mounted heat pump.
- Convert the existing Office and Store off the Small Gymnasium into a Cardio area with new steel portal frames opening one side to the Small Gymnasium.