You are not logged in.

MDC1518-6 Churchill Bridge Replacement & MDC1502-3 Makiekie Replacement

This tender is using the new split file responses feature on GETS. The agency has indicated that they would like to receive responses separated by price and non price components. Please keep this in mind when preparing your response for submission via GETS.

Details

Tender Closed
RFx ID : 30138502
Tender Name : MDC1518-6 Churchill Bridge Replacement & MDC1502-3 Makiekie Replacement
Reference # :
Open Date : Thursday, 5 September 2024 4:00 PM (Pacific/Auckland UTC+12:00)
Close Date  : Friday, 27 September 2024 4:00 PM (Pacific/Auckland UTC+12:00)
Tender Type : Registration of Interest (ROI)
Tender Coverage : All of Government  [?]
Categories :
  • 30000000 - Structures and Building and Construction and Manufacturing Components and Supplies
  • 72140000 - Heavy construction services
Regions:
  • Manawatu-Wanganui
Required Pre-qualifications : None
Contact : Tender Secretary
tender.secretary@mdc.govt.nz
06 3230000
Alternate Physical Delivery Address  :
Alternate Physical Fax Number  :
Overview

The primary project is to construct an 88 metre long bridge consisting of two 44 metre long spans across the Pohangina River on Churchill Road.
The secondary project is to construct a single 44 metre span bridge across Makiekie Stream on Pohangina West Road. This secondary project is dependent on the availability of funding.
The approaches to both bridges will need to be raised. This will require approximately 5000m3 of earthworks. The material for bulk earthworks will be supplied by Manawatu District Council at stockpiles adjacent to each site.
The bridge structures consist of three identical 44 metre long steel trusses (one at Makiekie and two at Churchill Rd). Eastbridge Ltd has been engaged directly by Manawatu District Council for the design phase.
Eastbridge Ltd is also the nominated subcontractor for the fabrication and delivery of the 44 metre long steel trusses. The successful contractor will be required to coordinate this work package with Eastbridge Ltd.
Bridge foundations will be reinforced concrete bored piles and bridge decks will be precast concrete slabs.
The contract will consist of two Separable Portions;

SP1 Churchill Rd bridge and approaches

SP2 Makiekie Stream bridge and approaches (subject to the availability of funding).